Lentilek schedule: how will the streets be closed?

HarmonogramThe lenses started. Work is in full swing and everyone in the housing estate may feel certain limitations. Especially drivers, for whom several streets will be temporarily closed due to the construction of new parking spaces and a new surface. However, the Skanska construction company must respect a number of conditions and must not close all roads at once. For the entire period of implementation will still be available min. 70 parking spaces in Jančova, Ivančická or Místecká streets (part of the affected area is only Místecká 567-569 including the car park). Continue reading “Lentilek schedule: how will the streets be closed?”

Front gardens and sidewalks in Místecká and Malkovského

Fandíme fialováLetňanské lentilky have been prepared from the very beginning with the great support of the inhabitants of the housing estate. Since the first presentation in September 2011, the project has been under public discussion and people can directly influence the appearance of their surroundings. Kuželova Street, Místecká or Malkovského are arranged within Lentilek as their inhabitants wished. Of course, the much-discussed front gardens remain and will be full of flowers and new shrubs. Continue reading “Front gardens and sidewalks in Místecká and Malkovského”

Perspective pine in Jancova street

WP_20140506_007The strip of promising pines in Jančova Street is in direct intervention by the planned changes and building modifications. In such cases of conflict between the building and valuable greenery, the procedure is in accordance with ČSN 83 9061 Protection of greenery during construction activities, which clearly determines the procedures that must be followed to minimize damage to trees. Continue reading “Perspective pine in Jancova street”

First parking spaces available

WP_20140512_013On Monday 12/5, the first new parking spaces, which were created within the Letňany lentils, were handed over for early use. There are a few places in Jančová Street and another at the end in Ivančická. Parking has been a big topic since the first Lentilek study was published. Especially in Ivančická it can be seen that the designers were looking for practically every meter that could be used for cars. Continue reading “First parking spaces available”

Current schedule of Lentilky

Harmonogram LL I 140531Letňany lentils are not an exceptional building that differs from others. Some activities go slower, others faster. In Ivančická we discovered panels under the grass. Next to Místecká 448, where a new car park is already open, there were again problems with sewerage. These are standard unpredictable issues that are addressed on every construction site. Click on the side image to see the current schedule valid at the end of May.

Councilor Mikulecký invited the children to ride around Lentilky

WP_20140610_004The construction of Letňany lentils is in full swing. Representative Jan Mikulecký agreed with Skanska on a program for children from Malkovského kindergarten. On Tuesday, June 10, they looked directly at the building. Skanska prepared an open day for them, so preschoolers had fun all morning. In addition to competitions, where children won a lot of gifts, the greatest interest was in the excavator or truck Tatra. The boys and girls looked into the cabin and “dredged” a bit. “They are already looking forward to having a new playground and swings that the Lentils will bring them after the holidays,” says Jan Mikulecký, deputy and councilor of the Prague 18 district. Continue reading “Councilor Mikulecký invited the children to ride around Lentilky”

Current schedule of Lentilky

Harmonogram LL I 140705Letňany lentils affect the lives of thousands of people in the housing estate and are not an exceptional building that differs from similar buildings in residential areas. Some activities go slower, others faster. In Ivančická we discovered panels under the grass. Next to Místecká 448, where a new car park is already open, there were again problems with sewerage. These are standard unpredictable issues that are addressed on every construction site. The situation changes every day. Continue reading “Current schedule of Lentilky”

Jančova will be open after the weekend

WP_20140716_005From next year, drivers will be able to use dozens of new parking spaces. Jančova Street has been given a new surface and vertical parking spaces will be on both sides. As part of the Lentilek project, the original pines were also preserved, for which special protective countermeasures were implemented during construction. Jančova will be passable along Kuželova Street for the time being, it will be completely open until Ivančická in October.

The car parks in Místecká and Kuželova streets will be closed from 21/7

The car park in front of Místecká 567 – 569 will be closed from 21/7. The entire crossroads Místecká x Jančova x Jablunkovská will be impassable for several weeks. Before closing the whole area, Jančova Street will be opened with dozens of new parking spaces. Drivers can park their cars in newly created places.

Kuželova Street will also be closed from 21/7. Entry will be allowed only to construction machinery and cars of the construction contractor. We apologize to the drivers for the traffic restrictions.

More parking in Jančov

WP_20140720_013The first new part of Jančová Street is open from 21/7. Dozens of new parking spaces could be filled by drivers the weekend before the opening. Jančova Street has been given a new surface and vertical parking spaces are on both sides. As part of the Lentilek project, the original pines were also preserved, for which special protective countermeasures were implemented during construction. The entrance to the street in the coming weeks will be only from Místecká. Drivers will fully enjoy Jančov from October. Continue reading “More parking in Jančov”